Individual Residence - Requirements

The following is required to process your application for new residential service:

  • Completed application
  • Required documents outlined on application
  • Design Fee

 

Application

Application for Individual Residence (pdf).

Mail your completed application, required documents, and design fee to:

United Power, Inc.
Consumer Relations & Electric Design Dept.
PO Box 929
Brighton, CO 80601
-or-
500 Cooperative Way
Brighton, CO 80603

Incomplete application packets will not be processed.

 

After Receipt of Completed Application Packet:

  • A representative of United Power will contact you to meet on site if necessary.
  • Approximately 21 days after receipt of your completed application, you will receive a copy of the line extension design, an Agreement for Electric Line Extension and an invoice for the cost of the required electric line installation.
  • Upon receipt by United Power of the signed Agreement for Electric Line Extension, the signed Private Utilities Locate Form, and payment of the invoiced amount, and upon aquisition of any required easements and permits, a United Power representative will contact you to arrange for verification that the site is ready for electric line extension construction.
  • Once the site is ready, United Power Operations personnel will schedule construction of the electric line extension. Depending on the current construction schedule, construction of the line extension will begin between one to three weeks following confirmation that the site is ready.

 

Locating of Existing Underground Utilities

In compliance with Colorado State SB93-155, all existing underground utilities and other facilities must be marked prior to excavation. United Power will call the Utility Notification Center of Colorado 48 hours prior to the start of any excavation and request marking of all public utilities.

It is the customer's responsibility to verify, mark and provide a sketch of all customer-owned underground utilities and other facilities within the area of planned excavation. (Subdivision, Commercial/Industrial, and Multi-Unit Commercial builders: these utilities include developer installed water, sanitary sewer, storm sewer and irrigation facilities installed in conjunction with a subdivision or other land development project not yet accepted by the affected jurisdiction.)

United Power construction will not begin until all underground lines and private facilities are marked and United Power has received a sketch and signed copy of the Private Facilities form (pdf).

 